Expected Year of commissioning: 2020
-
Location: 22 km north-west from Kara. 4 km south-west from Sarakawa
-
River: Kara, Volta River Basin
-
Watersheed: 2,767 km2
-
Average annual discharge: 32.30 m3/s
-
Dam height: 44.5 m and 500m lenght, with a neck dam height of 10m and 760m long
-
Utilization factor: 50%
-
Maximum power: 24.2 MW
-
Turbines: 2 vertical Francis turbines with a unit capacity of 12.1 MW (93%)
-
Estimated annual production: 105,7 GWh
-
Electricity distribution: 161 kV (conditioned by the futute transmission line Kara – Dapaong). Variant: in 66 kV to Kara (27 km)
-
Cost of production works: 52.8M EUR
-
Cost of Energy Evacuation Structure: 7.7M EUR
-
Ration Million EUR / MW: 2.5
-
Investment CAPEX: 60.49M EUR
-
Estimated production cost: 0,057 EUR / kWh; 37,71 FCFA / kWh
-
Supported by: EU, AFD and the European Bank of Investment (EBI)
More info: Agence Togolaise d'Electrification Rurale et des Energies Renouvelables (AT2ER)