Gorou Banda

Description

Inaugurated in April 2017, the Gorou Banda diesel power plant improves supply to Niamey and reduce dependence on the interconnection with Nigeria. The project was financed by the government, the West African Development Bank and the Islamic Development Bank at a cost of CFA75.4bn.The plant, located 5km south of Niamey with four 20MW diesel turbines, was built by Sinohydro, which started construction in April 2013. The construction of lines and substations was carried out by Chinese company TBEA.

Info

Capacité actuelle installée: 

100.00MW

Connexion: 

Ongrid

Situation actuel: 

Operational

Coût d'investissement: 

114 608 000.00€