Usman Dam Water Treatment Plant Solar PV

Description

Year of commissioning of phase I (975Kwp): August 2016

Year of commisioning of phase II (220 KWp): January 2017

Developer: Federal Capital Territory Water Board (FCTWB), Government of Nigeria

Contractor / EPC: Toyota Tsusho Corporation, Japan; Subcontract to Crown Agents Limited, Japan

Beneficiary: FCT water board (Lower Usuma Dam, Bwari, Abuja)

Source of funding: Japan International Cooperation Agency (JICA)

According to the Federal Ministry of Power, Water and Houses, the project will:

  • increase Annual Energy Generation by 1,496MWh
  • reduce the Water Treatment Electricity bill by N31.5M/Year
  • reduce Fossil Fuel use by 334,613Nm/year
  • reduce CO2 Emission : 741.9 tonnes

 

Info

Capacité actuelle installée: 

1.20MW

Connexion: 

Ongrid

Situation actuel: 

Operational

Coût d'investissement: 

7 950 740.00€

Catégorie: 

Observatory Country: 

Système financier

Subvention: 

100.00%
Investisseurs
JICA - Japan International Cooperation Agency

.