Bushrod 3

Description: 

Year of commissioning: 2016

Project funded by JICA (Japan Intenational Coperation Agency)

More information HERE [1]

Observatory Country: 

Liberia

Type: 

Heavy Fuel

Connection: 

Ongrid

Investment Cost: 

25 000 000.00€

Current Status: 

Operational

INSTALLED CAPACITY (operational plants) or PLANNED CAPACITY (planned plants): 

10.00MW

Source URL (modified on 03/07/2017 - 14:26): http://www.ecowrex.org/eg/bushrod-3

Links
[1] https://constructionreviewonline.com/2016/09/liberia-commissions-a-10mw-heavy-fuel-oil-power-plant/