The project is promoted by SABER/ABREC and will be the biggest grid connected PV plant in Guinea Bissau. It has a capacity of 20 MW and consists of 16 units of 1,250 kW each. The plant in Bor will be financed by BOAD. [1]
Expected year of commissioning: 2020
The tender process finalized in March 2019 and it is supported by SABER-ABREC [2] - The Chinese state-owned company Sinohydro won the engineering, procurement and construction (EPC) contract