Gomoa Onyaadze

Descrição

Year of commissioning: September 2018

- 40,800 polycrystalline silicon panels

- 400 inverters

- The estimated 20 megawatt power generation will strengthen the national electricity grid by powering the substation of the Ghana Electricity Company (ECG) of Winneba, a town of nearly 50,000 inhabitants, located 60 km from the capital Accra. It was financed and built by Meinergy Ghana, a local company that also manages and maintains the plant.

- It is located next to the Oyandze 20 MW solar plant, which is in operation since 2016

Informações

INSTALLED CAPACITY (operational plants) or PLANNED CAPACITY (planned plants): 

20.00MW

Connection: 

Ongrid

Current Status: 

Operational

Investment Cost: 

26 000 000.00€

Type: 

Observatory Country: 

RE&EE Category: 

  • Foto voltaico
  • Parque solar ligado a rede

.