Gomoa Onyaadze

Description

Year of commissioning: September 2018

- 40,800 polycrystalline silicon panels

- 400 inverters

- The estimated 20 megawatt power generation will strengthen the national electricity grid by powering the substation of the Ghana Electricity Company (ECG) of Winneba, a town of nearly 50,000 inhabitants, located 60 km from the capital Accra. It was financed and built by Meinergy Ghana, a local company that also manages and maintains the plant.

- It is located next to the Oyandze 20 MW solar plant, which is in operation since 2016

Info

Capacité actuelle installée: 

20.00MW

Connexion: 

Ongrid

Situation actuel: 

Operational

Coût d'investissement: 

26 000 000.00€

Catégorie: 

Observatory Country: 

Catégorie des EnR et de l’EE: 

  • Photovoltaïque
  • Centrale solaire pv connectée au réseau

.